The project includes the complete upgrade of the cogeneration plant and air systems of the mill’s PM4 and PM5.
Toscotec
PM1 produces packaging paper grades, including fluting, testliner, kraft paper, and gypsum board.
The start-up is scheduled for the Q4 2024.
Designed for optimal energy efficiency, the new AHEAD 1.8 machine features an upgraded design TT NextPress shoe press, a third-generation TT SYD Steel Yankee Dryer, and high efficiency TT Hood.
Hengan’s second TAD machine will be installed at their headquarters production base in Fujian province, and it is scheduled for start-up in 2024.
The project includes modifications to the machine for the new steam system and it is planned for start-up in the Q3 2024.
This new order involves an upgrade of the existing hybrid system configuration. In order to increase PM1’s drying capacity, Toscotec will install a TT Hood-Duo system with two separate circuits of heated air, one to the wet end hood and the other to the dry end.
The start-up is planned for the second half of 2024.