Capacity will rise to more than 5 million board feet a month, and drying time will fall to 24 hours or less.

Capacity will rise to more than 5 million board feet a month, and drying time will fall to 24 hours or less.

The longtime IKEA supplier is exiting solid-wood furniture to focus on prefabricated construction and general contracting.

Reels go up from January 1 and sheets from January 11; finishing and converting services will also cost more.

The province widened the program to cover capital spending on equipment and infrastructure and amended its Forests Act.

Laurie Brlas will leave the board at year-end after nearly eight years of service.

Separation is expected on December 7, and International Paper will keep about a 19.9% stake in the new company.

The mill could make about 190 thousand metric tons a year of dissolving grade pulp, and about 350 employees were affected.

The province is providing C$2.35 million to its forestry sector, hit by U.S. tariffs and duties on softwood lumber.

Employment at the forest and mill could reach 220 to 250 people after a four-to-six-week stoppage.

Michigan mills get only about half of their logs from in-state forests, less than mills in Wisconsin or Minnesota.

Kenneth Sachse will assume CFO duties while the company searches for a permanent successor.

Covered storage protects materials from Phoenix's extreme weather as the branch widens its product range.

The work was split into six stages, with three weeks of downtime per line.

Fuelwood Finland plans to start production in the first quarter of 2027 and restart a power plant on the site.

Two new short-cycle presses can laminate about 16 million square meters of particleboard a year.

The mill would have made 240,000 metric tons of tissue paper a year and created 400 jobs.

Ecostrat, the company running the program, expects more than C$1 billion in new projects in those regions within two years.

Restart is planned for 2027, after which the plant will join the company's existing Burney operations.

The two pulp mills took 2.5 million tons of pulpwood a year and owe suppliers more than Euro 5 million.

Chief operating officer for the West John Lesher will also retire, at the end of 2026.